Sec. 31.41 Financial reporting.
(a) General. (1) Except as provided in paragraphs (a) (2) and (5) of
this section, grantees will use only the forms specified in paragraphs
(a) through (e) of this section, and such supplementary or other forms
as may from time to time be authorized by OMB, for:
(i) Submitting financial reports to Federal agencies, or
(ii) Requesting advances or reimbursements when letters of credit
are not used.
(2) Grantees need not apply the forms prescribed in this section in
dealing with their subgrantees. However, grantees shall not impose more
burdensome requirements on subgrantees.
(3) Grantees shall follow all applicable standard and supplemental
Federal agency instructions approved by OMB to the extent required under
the Paperwork Reduction Act of 1980 for use in connection with forms
specified in paragraphs (b) through (e) of this section. Federal
agencies may issue substantive supplementary instructions only with the
approval of OMB. Federal agencies may shade out or instruct the grantee
to disregard any line item that the Federal agency finds unnecessary for
its decisionmaking purposes.
(4) Grantees will not be required to submit more than the original
and two copies of forms required under this part.
(5) Federal agencies may provide computer outputs to grantees to
expedite or contribute to the accuracy of reporting. Federal agencies
may accept the required information from grantees in machine usable
format or computer printouts instead of prescribed forms.
(6) Federal agencies may waive any report required by this section
if not needed.
(7) Federal agencies may extend the due date of any financial report
upon receiving a justified request from a grantee.
[[Page 399]]
(b) Financial Status Report--(1) Form. Grantees will use Standard
Form 269 or 269A, Financial Status Report, to report the status of funds
for all nonconstruction grants and for construction grants when required
in accordance with Sec. 31.41(e)(2)(iii).
(2) Accounting basis. Each grantee will report program outlays and
program income on a cash or accrual basis as prescribed by the awarding
agency. If the Federal agency requires accrual information and the
grantee's accounting records are not normally kept on the accrual basis,
the grantee shall not be required to convert its accounting system but
shall develop such accrual information through and analysis of the
documentation on hand.
(3) Frequency. The Federal agency may prescribe the frequency of the
report for each project or program. However, the report will not be
required more frequently than quarterly. If the Federal agency does not
specify the frequency of the report, it will be submitted annually. A
final report will be required upon expiration or termination of grant
support.
(4) Due date. When reports are required on a quarterly or semiannual
basis, they will be due 30 days after the reporting period. When
required on an annual basis, they will be due 90 days after the grant
year. Final reports will be due 90 days after the expiration or
termination of grant support.
(c) Federal Cash Transactions Report--(1) Form. (i) For grants paid
by letter or credit, Treasury check advances or electronic transfer of
funds, the grantee will submit the Standard Form 272, Federal Cash
Transactions Report, and when necessary, its continuation sheet,
Standard Form 272a, unless the terms of the award exempt the grantee
from this requirement.
(ii) These reports will be used by the Federal agency to monitor
cash advanced to grantees and to obtain disbursement or outlay
information for each grant from grantees. The format of the report may
be adapted as appropriate when reporting is to be accomplished with the
assistance of automatic data processing equipment provided that the
information to be submitted is not changed in substance.
(2) Forecasts of Federal cash requirements. Forecasts of Federal
cash requirements may be required in the ``Remarks'' section of the
report.
(3) Cash in hands of subgrantees. When considered necessary and
feasible by the Federal agency, grantees may be required to report the
amount of cash advances in excess of three days' needs in the hands of
their subgrantees or contractors and to provide short narrative
explanations of actions taken by the grantee to reduce the excess
balances.
(4) Frequency and due date. Grantees must submit the report no later
than 15 working days following the end of each quarter. However, where
an advance either by letter of credit or electronic transfer of funds is
authorized at an annualized rate of one million dollars or more, the
Federal agency may require the report to be submitted within 15 working
days following the end of each month.
(d) Request for advance or reimbursement--(1) Advance payments.
Requests for Treasury check advance payments will be submitted on
Standard Form 270, Request for Advance or Reimbursement. (This form will
not be used for drawdowns under a letter of credit, electronic funds
transfer or when Treasury check advance payments are made to the grantee
automatically on a predetermined basis.)
(2) Reimbursements. Requests for reimbursement under nonconstruction
grants will also be submitted on Standard Form 270. (For reimbursement
requests under construction grants, see paragraph (e)(1) of this
section.)
(3) The frequency for submitting payment requests is treated in
Sec. 31.41(b)(3).
(e) Outlay report and request for reimbursement for construction
programs. (1) Grants that support construction activities paid by
reimbursement method.
(i) Requests for reimbursement under construction grants will be
submitted on Standard Form 271, Outlay Report and Request for
Reimbursement for Construction Programs. Federal agencies may, however,
prescribe the Request for Advance or Reimbursement form, specified in
Sec. 31.41(d), instead of this form.
[[Page 400]]
(ii) The frequency for submitting reimbursement requests is treated
in Sec. 31.41(b)(3).
(2) Grants that support construction activities paid by letter of
credit, electronic funds transfer or Treasury check advance. (i) When a
construction grant is paid by letter of credit, electronic funds
transfer or Treasury check advances, the grantee will report its outlays
to the Federal agency using Standard Form 271, Outlay Report and Request
for Reimbursement for Construction Programs. The Federal agency will
provide any necessary special instruction. However, frequency and due
date shall be governed by Sec. 31.41(b) (3) and (4).
(ii) When a construction grant is paid by Treasury check advances
based on periodic requests from the grantee, the advances will be
requested on the form specified in Sec. 31.41(d).
(iii) The Federal agency may substitute the Financial Status Report
specified in Sec. 31.41(b) for the Outlay Report and Request for
Reimbursement for Construction Programs.
(3) Accounting basis. The accounting basis for the Outlay Report and
Request for Reimbursement for Construction Programs shall be governed by
Sec. 31.41(b)(2).