[CITE: 40CFR30.51]

[Page 368-369]
 
                   TITLE 40--PROTECTION OF ENVIRONMENT
 
               CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY
 
PART 30_UNIFORM ADMINISTRATIVE REQUIREMENTS FOR GRANTS AND AGREEMENTS 
WITH INSTITUTIONS OF HIGHER EDUCATION, HOSPITALS, AND OTHER NON-PROFIT 
 
                    Subpart C_Post-Award Requirements
 
Sec. 30.51  Monitoring and reporting program performance.

    (a) Recipients are responsible for managing and monitoring each 
project, program, subaward, function or activity supported by the award. 
Recipients shall monitor subawards to ensure subrecipients have met the 
audit requirements as delineated in Sec. 30.26.
    (b) EPA shall prescribe the frequency with which the performance 
reports shall be submitted. Except as provided in paragraph (f) of this 
section, performance reports shall not be required more frequently than 
quarterly or, less frequently than annually. Annual reports shall be due 
90 calendar days after the grant year; quarterly or semi-annual reports 
shall be due 30 days after the reporting period. EPA may require annual 
reports before the anniversary dates of multiple year awards in lieu of 
these requirements. The final performance reports are due 90 calendar 
days after the expiration or termination of the award.
    (c) If inappropriate, a final technical or performance report shall 
not be required after completion of the project.
    (d) When required, performance reports shall generally contain, for 
each award, brief information on each of the following.
    (1) A comparison of actual accomplishments with the goals and 
objectives established for the period, the findings of the investigator, 
or both. Whenever appropriate and the output of programs or projects can 
be readily quantified, such quantitative data should be related to cost 
data for computation of unit costs.
    (2) Reasons why established goals were not met, if appropriate.
    (3) Other pertinent information including, when appropriate, 
analysis and explanation of cost overruns or high unit costs.
    (e) Recipients shall not be required to submit more than the 
original and two copies of performance reports.
    (f) Recipients shall immediately notify EPA of developments that 
have a significant impact on the award-supported activities. Also, 
notification shall be given in the case of problems, delays, or adverse 
conditions which materially impair the ability to meet the objectives of 
the award. This notification shall include a statement of the action 
taken or contemplated, and any assistance needed to resolve the 
situation.

[[Page 369]]

    (g) EPA may make site visits, as needed.
    (h) EPA shall comply with clearance requirements of 5 CFR part 1320 
when requesting performance data from recipients.