Sec. 6.904 Environmental review process.
(a) Environmental review. (1) An environmental review shall be
conducted when the program of requirements or scope of work has been
completed for the construction, improvements, or modification of special
purpose facilities. For special purpose facility construction, the
Chief, Facilities Engineering and Real Estate Branch, shall request the
assistance of the appropriate program office and Regional Administrator
in the review. For modifications and improvement, the appropriate
responsible official shall request assistance in making the review from
other cognizant EPA offices.
(2) Any environmental information documents requested shall contain
the same sections listed for EISs in subpart B. Contractors and
consultants shall be notified in contractual documents when an
environmental information document must be prepared.
(b) Notice of intent, EIS, and FNSI. The responsible official shall
decide at the completion of the Environmental review whether there may
be any significant environmental impacts. If there could be significant
environmental impacts, a notice of intent and an EIS shall be prepared
according to the procedures under subparts A, B, C and D. If there are
not any significant environmental impacts, a FNSI shall be prepared
according to the procedures in subparts A and D. The FNSI shall list
[[Page 132]]
any mitigation measures necessary to make the recommended alternative
environmentally acceptable.
(c) Timing of action. Pursuant to Sec. 6.401(b), in no case shall a
contract be awarded or construction activities begun until the
prescribed 30-day wait period for a final EIS has elapsed. Similarly,
under Sec. 6.400(d), no action shall be taken until the 30-day comment
period for FNSIs is completed.