Sec. 6.803 Environmental review process.
(a) Environmental information. (1) Environmental information
documents shall be submitted to EPA by grant applicants or contractors.
If there is a question concerning the need for a document, the potential
contractor or grantee should consult with the appropriate project
officer for the grant or contract.
(2) The environmental information document shall contain the same
sections specified for EIS's in subpart B. Guidance alerting potential
grantees and contractors of the environmental information documents
shall be included in all grant application kits, attached to letters
concerning the submission of unsolicited proposals, and included with
all requests for proposal.
(b) Environmental review. An environmental review will be conducted
before a grant or contract award is made. This review will include the
preparation of an environmental assessment by the responsible official;
the appropriate Regional Administrator's input will include his
recommendations on the need for an EIS.
(c) Notice of intent and EIS. Based on the environmental review if
the criteria in Sec. 6.802 of this part apply, the responsible official
will assure that a notice of intent and a draft EIS are prepared. The
responsible official may request the appropriate Regional Administrator
to assist him in the preparation and distribution of the environmental
documents.
(d) Finding of no significant impact. If the environmental review
indicated no significant environmental impacts, the responsible official
will assure that a FNSI is prepared which lists any mitigation measures
necessary to make the recommended alternative environmentally
acceptable.
(e) Timing of action. Pursuant to Sec. 6.401(b), in no case shall a
contract or grant be awarded until the prescribed 30-day review period
for a final EIS has elapsed. Similarly, no action shall be taken until
the 30-day comment period for a FNSI is completed.