[Code of Federal Regulations]
[Title 40, Volume 1]
[Revised as of July 1, 2007]
From the U.S. Government Printing Office via GPO Access
[CITE: 40CFR6.508]
[Page 119]
TITLE 40--PROTECTION OF ENVIRONMENT
CHAPTER I--ENVIRONMENTAL PROTECTION AGENCY
PART 6_PROCEDURES FOR IMPLEMENTING THE REQUIREMENTS OF THE COUNCIL ON
ENVIRONMENTAL QUALITY ON THE NATIONAL ENVIRONMENTAL POLICY ACT--
Subpart E_Environmental Review Procedures for Wastewater Treatment
Construction Grants Program
Sec. 6.508 Finding of No Significant Impact (FNSI) determination.
(a) Criteria for producing and distributing FNSIs. If, after
completion of the environmental review, EPA determines that an EIS will
not be required, the responsible official shall issue a FNSI in
accordance with Sec. Sec. 6.105(f) and 6.400(d). The FNSI will be based
on EPA's independent review of the preliminary environmental assessment
and any other environmental information deemed necessary by the
responsible official consistent with the requirements of Sec. 6.506(c).
Following the Agency's independent review, the environmental assessment
will be finalized and either be incorporated into, or attached to, the
FNSI. The FNSI shall list all mitigation measures as defined in Sec.
1508.20 of this title, and specifically identify those mitigation
measures necessary to make the recommended alternative environmentally
acceptable.
(b) Proceeding with grant awards. (1) Once an environmental
assessment has been prepared and the issued FNSI becomes effective for
the treatment works within the study area, grant awards may proceed
without preparation of additional FNSIs, unless the responsible official
later determines that the project or environmental conditions have
changed significantly from that which underwent environmental review.
(2) For all environmental assessment/FNSI determinations:
(i) That are five or more years old on projects awaiting Step 2+3 or
Step 3 grant funding, the responsible official shall re-evaluate the
project, environmental conditions and public views and, prior to grant
award, either:
(A) Reaffirm--issue a public notice reaffirming EPA's decision to
proceed with the project without revising the environmental assessment;
(B) Supplement--update information and prepare, issue and distribute
a revised EA/FNSI in accordance with Sec. Sec. 6.105(f) and 6.400(d);
or
(C) Reassess--withdraw the FNSI and publish a notice of intent to
produce an EIS followed by the preparation, issuance and distribution of
the EIS/ROD.
(ii) That are made on projects that have been awarded a Step 2+3
grant, the responsible official shall, at the time of plans and
specifications review under Sec. 35.2202(b) of this title, assess
whether the environmental conditions or the project's anticipated impact
on the environment have changed and, prior to plans and specifications
approval, advise the Regional Administrator if additional environmental
review is necessary.
[51 FR 32612, Sept. 12, 1986]